# Room Based BIM III: Only the Wet Rooms Vote

- **Author**: Clifton Harness
- **Date**: September 4, 2024
- **Address**: /harness-architecture/room-based-bim-ii-2

Interactive study Only the wet rooms vote: a room table read down, then plumbing walls and stacks

In 2024 I made a table. Twenty rooms down the side, from mechanical room to bedroom, and across the top a live load and five services: water, waste, gas, power and air. A dot meant the room needs it. I was trying to describe a building as a set of rooms that know what they want, and the table was the first list of wants.

Read it across and each row is a shopping list. A kitchen wants water, waste, gas, power and air, on a floor designed for 40 pounds per square foot. A bedroom wants power and air. The drawing that went with the post did the obvious thing with those lists: pick some rooms and it added up the dots. Three rooms, three of them need power. True, and useless.

[Room Based BIM I](https://www.testfit.io/harness-architecture/room-based-bim.md) took the same idea down to the objects inside a room, a sink bringing its own water and drain to the nearest wall. This post goes the other way, up to the plan, and asks what a table like this is actually for. My answer is that you have to read it down, not across, and that when you do, most of it goes quiet.

## Read it down

Power is in all twenty rows. Air is in nineteen; the storage room is the only one that goes without. Water is in seven, waste is in the same seven, and gas is in four.

A column where every row says yes can’t tell you where anything goes. If every room needs power, power has no opinion about whether the bedroom sits next to the kitchen or across the hall from it. Wire still costs money, and plenty of it, but it costs about the same in every arrangement you could draw. If you’re writing software to rank plans, a feature that never changes is a constant, and a constant can’t choose between two plans. Power and air belong in the estimate. They don’t belong in the layout logic.

Water and waste never disagree. Every room in the table that wants a supply line wants a drain, and no room wants one without the other. Two columns that always agree are one column, so call it wet. That single bit, wet or dry, is the most useful thing in the whole table, and I had split it across two columns where it was easy to miss.

Here’s a confession that proves the point. My 2024 table said a break room needs no water. Every break room I’ve ever drawn had a sink, so the drawing fixes it. But notice what kind of mistake that was. If I’d left power off the closet row, nothing about any plan would change. Mark the break room dry and a room-based model will cheerfully put it in the middle of an office floor, forty feet from the nearest drain. Errors in the common columns are typos. Errors in the rare columns move walls.

Gas is rarer still, and it mostly rides along: three of the four gas rooms are already wet. The garage is the exception, for its unit heaters. With more cities pushing new buildings toward all-electric, the gas column is draining toward zero, and in housing the plan barely notices, because the kitchen was a wet room anyway.

## The load column says the same thing

Fourteen of the twenty rooms sit between 30 and 50 pounds per square foot. Those numbers size the slab everywhere and have no say in where rooms go. The corridor is at 80. The five rooms at 100 or more are the mechanical room, the fire pump room, storage, electrical and the server room. Every one of them is back-of-house, and every one of them has an opinion about location: on grade, on the podium, or on a slab somebody drew thick on purpose. The common value sets a thickness. The rare value picks a place.

## What one bit does to a plan

So what does a room-based model do with one bit? It counts walls. Here is a slice of a double-loaded apartment bar: eight one-bedroom units, four each side of a corridor, each 26 feet wide and 28 deep. The bath and the kitchen are the wet rooms, and in this unit they line up against one side wall, bath by the entry and kitchen behind it. Draw every unit in the same hand and every unit brings its own plumbing wall. Eight units, eight wet walls out of the ten side walls in the bar.

Watch the other meter. Every room in these units needs power, so every side wall in the bar has a powered room against it: ten of ten. It will read ten of ten whatever you do to this plan. That’s the power column, drawn.

Now mirror every other unit. The wet rooms meet back to back across the side wall, and one plumbing wall serves two units. Eight units, four plumbing walls. Every multifamily architect knows this move; it’s about the first thing you do to a unit plan. The point is that software can know it too, but only if the rooms carry the wet bit. A model made of walls has no idea which walls have a toilet on both sides.

Tap any unit in the drawing to flip it, and watch the water count move while the power count sits still.

Then the trade-off. Residents want the bath by the bedroom, not by the front door. Move every bath to the far side of its unit and each unit now has wet rooms on both side walls. The count goes to ten of ten, and here’s the funny part: it stays at ten however you hand the units, because every side wall now has a kitchen on one face or a bath on the other.

Sometimes that’s worth it. A luxury unit can carry a second wet wall; a workforce housing deal usually can’t. I don’t want the model to forbid it. I want it to price it: here’s your extra plumbing wall, here’s what it costs, decide with the number in front of you. Tap a bath to move it back and forth.

## Wet over wet

Plumbing walls are the cheap half of the problem. Drains run down, and they want to run straight down. This is the same bar cut in section along one side of the corridor, five floors, at the same scale as the plan. With mirrored pairs on every floor there are two stacks, and each one runs from the ground to the roof without a bend.

Now flip one unit on the third floor. Maybe it’s a different unit type, maybe somebody liked the view better the other way. Its kitchen and bath land on a wall with no drain below it. The waste has to run sideways through the ceiling of the floor below to find a stack, and a drain has to slope, about a quarter inch per foot for the small pipes. Twenty-six feet sideways is six and a half inches of fall, which buys you a soffit in somebody’s living room, a lower ceiling, or a deeper floor across the whole building. One flipped unit, one offset.

Tap any unit on any floor to try your own. Flip a whole floor and you get five offsets at once, because the floor above has to find its way back too. Flip the same unit on every floor and you get none: the stack just moves with it. That is the rule a room-based model should hold. Wet over wet, dry over dry, and a cost on every wet room that sits on a dry one.

## The judgment

A room requirement table is not a feature list. It’s a set of columns, and most of them are furniture: true everywhere, fine for the estimate, useless for the plan. The columns worth modeling are the rare ones, and in housing the rare one that costs real money is wet. If I were building this again I would start with one column, not five, and make the software count plumbing walls and offsets before it counted anything else.

The first version of this post also carried a long code table about how much floor area one door can serve. I’ve cut it. That question deserves its own post, and it got one in Portals III.

What this isn’t: plumbing design. The model knows nothing about fixture units, pipe sizes, vents, cleanouts, fire stopping or sound. A wet wall stands in for a chase and a riser, and a quarter inch per foot is the usual minimum slope for small drains, not a takeoff. What it does establish is the bookkeeping: which rooms carry the bit that matters, and how many walls and bends a plan spends on it.