Lead times enter the building schedule
Four floors, coordinated deliveries
Drag the steel or glazing delivery marker. Drag floor count beside the material quantities.
Current geometryDirect edit / changed part
4 floors × 60 tons steel and 24 windows. Installation assumptions: frame 1.5 weeks/floor, envelope 0.75, interiors 1.25, then 2 weeks closeout.
Explicit illustrative procurement network. Steel and glazing fabrication start together; framing waits for steel, envelope waits for framing and glazing, interiors follow envelope, and closeout follows interiors. Durations and quantities are stated assumptions, not a forecast of an actual project.